This system at Ozone Park, Howden was installed and commissioned late in 2015. The installation comprising of 576 modules took just under two weeks to complete. Connection to the TNT warehouse on site allows them access to renewably generated energy all year round.
Minimal disturbance was created for the occupants as all trenching work between the installation and the point of connection was undertaken using moling devices. A power outage was neutralised through Discover Energy connecting a back-up generator to the distribution centre enabling operations to continue to run smoothly. Once up and running this system provided power to an array of equipment including lights, air conditioning units, conveyors systems and battery charging stations.